Revenue budget 2023/24 and capital programme 2023/24 to 2027/28

Decision Maker: Cabinet, Council

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Purpose:

Purpose: to recommend Council to approve the budget

Decisions:

Cabinet considered the head of finance’s report on the draft revenue budget for 2023/24 and the draft capital programme to 2027/28.  The report brought together information to allow Cabinet to recommend its budget to Council.  The report contained the medium term financial plan detailing a model budget for the next five years.  The report also contained the opinion of the council’s chief finance officer on the robustness of estimates and the adequacy of the council’s reserves. 

 

The Cabinet member for finance proposed a balanced budget.  It included £0.5 million of discretionary spending and used only £0.7 million from reserves.  Officers and members had worked hard in balancing the budget at a time of great economic uncertainty, resulting in assumptions being made in the medium term financial plan.  High inflation had put pressure on the council’s spending, and there was uncertainty over government funding beyond 2024/25.  Another uncertainty was whether the council would be required to pay an additional £5 million to the pension fund.  The triennial pension fund valuation might require this and so provision had been made for this possibility.  The budget also included new capital funding for a new leisure facility at north-east Didcot, a new learner pool at The Wave in Didcot, and funding for the decarbonisation project at the Cornerstone Arts Centre.  Council tax would increase by £5 for a Band D property, the maximum allowed without holding a referendum.  This increase equated to less than 10 pence per week. 

 

Cabinet noted that Scrutiny Committee had considered the draft budget and had received a briefing from the head of finance.  The committee discussed the proposed new leisure facility at north-east Didcot.  The intention was for this to be part-funded by Vale of White Horse District Council as its residents could benefit from this facility.  The committee recommended to Cabinet that officers should consult the council’s Legal team to consider whether the council should enter into a contract with the Vale to formalise the funding agreement.  Cabinet welcomed Scrutiny Committee’s suggestion but considered that this need not be actioned at this stage.  The first step was for both councils to allocate sufficient funds in their budgets and for the project to be progressed further before a decision could be made on whether a contractual position was required between the two councils. 

 

Cabinet members were proud of the budget.  It provided discretionary spending to allow the council to continue funding the community hub.  The government funding for this was coming to an end.  The hub had proved successful, providing support to the residents through the Covid-19 pandemic and during the cost-of-living crisis.  It had also supported refugees and host families in the district.  The budget also provided support for the voluntary and community sector, which supported the most vulnerable.  There was investment in new leisure facilities and support for the decarbonisation project at the Cornerstone.  An allocation had also been made to contribute to the Local Authority Housing Fund, a new project introduced by the government.  This brought in capital funding, which was matched in the budget to provide homes to meet local need.  The use of section 106 funds and Community Infrastructure Levy income had supported the council’s capital programme.  There was money for additional lawyers and funding for the new voter photo identification project due to be introduced at the May 2023 local elections. 

 

In conclusion, Cabinet welcomed the proposed budget.  It was a balanced budget with minimal draw from reserves.  The council was now in a better financial position and able to deliver its corporate plan, while planning for the future with new homes and infrastructure and retaining the community hub to provide for those most in need. 

 

Cabinet noted the confidential appendix D2 to the report and decided that it was unnecessary to discuss it in exempt session.  

 

Cabinet thanked the Cabinet member for finance, the head of finance and his team, and all budget holders for their work in preparing and balancing the budget. 

 

RECOMMENDED to Council to:

 

(a)       set the revenue budget for 2023/24, as set out in appendix A.1 to the head of finance’s report to Cabinet on 2 February 2023;

 

(b)       authorise the head of finance, in consultation with the cabinet member for finance, to make a one-off contribution to the Oxfordshire County Council pension fund of up to £5 million, subject to confirmation of the results of the triennial pension fund valuation;

 

(c)        approve the capital programme for 2023/24 to 2027/28, as set out in appendix D.1 to the report, together with the capital programme changes as set out in appendix D.2 and Appendix D.3 to the report;

 

(d)       set the council’s prudential limits as listed in appendix E to the report;

 

(e)       approve the medium-term financial plan to 2027/28, as set out in appendix F to the report;

 

(f)         allocate £500,000 to fund the Communities Capital and Revenue grant scheme; and

 

(g)       ask officers to review the Medium Term Financial Strategy at the end of the current spending review period. 

 

RESOLVED: to agree that the head of finance, in conjunction with the Cabinet member for finance, may make minor adjustments to the report and the prudential indicators, should they prove necessary prior to its submission to Council on 16 February 2023. 

 

Report author: Richard Spraggett

Publication date: 13/02/2023

Date of decision: 02/02/2023

Decided at meeting: 02/02/2023 - Cabinet

Accompanying Documents:

 

Contact us - Democratic services

Phone icon

01235 422520
(Text phone users add 18001 before dialing)

Address icon

South Oxfordshire District Council
Abbey House, Abbey Close,
Abingdon
OX14 3JE